Who We Serve Services How We Engage Case Studies Why Wayfield Footprint News Start a project →

Case Studies

How each service line plays out in practice.

Wayfield Energy Consulting is a newly formed firm, so rather than dress up marketing copy as client history, each item below is a realistic scenario built around a specific service — paired with a real, independently documented project that illustrates the same dynamic.

How to read these: every entry is a Representative Case Study — a realistic scenario illustrating what a Wayfield engagement of that type looks like, not a claim that Wayfield performed the work described. Where an entry cites a real project as an "Evidence Basis," that work was performed by the named third party (linked to a public source), not by Wayfield. We'll convert these to real, named client case studies as WEC completes engagements it has permission to publish.
Service:
Region:
Representative

Feasibility Screen Kills a Bad Site Before It Costs Anything

Development Advisory · ERCOT, Texas

Client

Mid-size U.S. renewable-energy developer

The challenge

The developer was evaluating a prospective solar site that looked attractive from a land and resource perspective, with a nearby substation that appeared to offer a workable interconnection path. The risk: a site can look excellent at the land-acquisition stage and still turn uneconomic once interconnection requirements, network upgrades, congestion exposure, and project yield are factored in. ERCOT's interconnection queue holds a very large volume of proposed generation, which makes early screening increasingly important before a developer commits real engineering and development capital.

Advisory approach

A development screen evaluates:

  • Point-of-interconnection options
  • Substation voltage and configuration
  • Existing generation and load
  • Queue position and competing projects
  • Preliminary upgrade exposure
  • Transmission/distribution constraints
  • Expected project yield
  • Land and permitting constraints
  • Estimated CAPEX
  • Expected LCOE / PPA economics
  • Sensitivity to interconnection costs

Result

The site is screened out before significant detailed-engineering spend. The lesson: the cheapest land is not necessarily the cheapest project.

Kill marginal projects early. Spend development capital only where the grid, land, and economics work together.
Evidence basis: ERCOT research has shown why project selection can't rest on resource quality alone — interconnection location, transmission constraints, and system conditions materially affect renewable-project economics. This context comes from published ERCOT/industry analysis, not from a Wayfield engagement.
Representative

EPC-Ready Design Package in Under 12 Weeks

Engineering & Design · U.S. / ERCOT

Client

Independent solar developer

The challenge

The developer needed to move quickly from development concept to an EPC-ready package against a narrow interconnection and procurement schedule. The danger: letting the engineering package itself become the critical path.

Scope

  • Preliminary and detailed site layout
  • DC/AC sizing and equipment selection
  • Single-line diagram and MV collection concept
  • Inverter/transformer configuration and protection concept
  • Interconnection documentation and electrical calculations
  • Civil design criteria and design basis
  • Equipment specifications and EPC technical requirements
  • Grid-compliance documentation

Approach

Engineering is organized around the commercial decision gates rather than treated as an isolated technical exercise — resolving the major EPC and interconnection decisions early enough that procurement can begin without waiting on every downstream drawing.

Result

The developer receives an EPC-ready technical package sufficiently developed to support procurement and interconnection activities in parallel rather than in sequence.

Engineering should accelerate development — not become another development bottleneck.
Evidence basis: Electric Power Engineers (EPE) provided preliminary design and owner's-engineer support for Elawan Energy's 50 MW Pitts Dudik Solar Project in Texas — including main power transformer specification and bid evaluation, EPC bid evaluation, interconnection-station design review, substation design review, and construction-phase technical support. EPE case study → That work was performed by EPE for Elawan Energy, not by Wayfield.
Representative

Bid Evaluation Framework Saves a Developer From the Cheapest-Looking EPC

RFP & Procurement Support · United States

Client

Independent developer — 30+ MW solar project

The challenge

Three EPC contractors submit bids. The lowest bid initially looks like the strongest commercial value — but comparing EPC prices alone is misleading when the bids aren't actually equivalent in scope.

Evaluation framework

  • EPC price — normalized across scope
  • Scope exclusions — identified
  • Module/BOS assumptions — normalized
  • Performance guarantee — tested
  • Liquidated-damages structure — reviewed
  • Warranty — reviewed
  • Staffing plan — reviewed
  • Schedule — risk-weighted
  • Change-order exposure — evaluated
  • Financial strength — evaluated
  • O&M assumptions — evaluated
  • Technical compliance — scored

Finding

The lowest-price contractor's apparent advantage narrows substantially once exclusions, warranty limitations, staffing assumptions, and performance-risk exposure are incorporated.

Result

The developer can make the award decision on risk-adjusted project cost rather than nominal EPC price.

The cheapest EPC bid is only cheap until you discover what isn't included.
Evidence basis: This framework reflects standard, widely published EPC-procurement guidance emphasizing scope normalization, bill-of-materials transparency, performance guarantees, liquidated damages, and warranty terms over ranking bids on headline EPC price alone — general industry practice, not a specific Wayfield engagement.
Representative

Rural Electric Cooperative Scopes Its First Community Solar Project

Development Advisory · United States

Client

Electric cooperative

The challenge

A rural cooperative wants to explore community solar but has no established internal development model. The first question — how large should the project be — doesn't necessarily have "as large as possible" as the right answer.

Advisory approach

The feasibility analysis examines member demand, subscriber participation, load profiles, available land, interconnection capacity, project CAPEX, subscription pricing, member savings, financing structure, utility return, O&M costs, and sensitivity to project size.

Result

Instead of sizing the project around developer sales targets, the cooperative sets project size based on actual member economics and grid constraints.

Community solar should be sized around the customer — not around the developer's maximum possible MW.
Evidence basis: NRECA and the National Community Solar Partnership have published business-case tools specifically to help cooperatives evaluate community-solar economics, including the tradeoff between member savings and utility/project returns; NREL has published related research on structuring community solar to be more cost-effective and scalable for cooperatives and municipal utilities. These are third-party published tools and research, not a Wayfield engagement.
Representative

Owner's Engineer Oversight Catches a Commissioning Shortcut

Owner's Engineer · United States

Client

Municipal utility

The challenge

Construction is approaching energization. The EPC team, under schedule pressure, proposes moving quickly through final commissioning activities. The owner's question is simple: is the plant actually ready to energize?

Independent review

The Owner's Engineer reviews protection settings, relay coordination, CT/PT ratios, trip logic, SCADA points, interlocks, grounding, transformer protection, breaker operation, protection test results, and commissioning documentation.

Finding

The independent review identifies a protection-setting discrepancy before energization — caught during commissioning rather than discovered after the facility is already connected.

Why independence matters

The Owner's Engineer represents the asset owner, not the EPC. That separation creates an independent technical checkpoint between "the EPC says we're ready" and "the asset is actually ready to energize."

The last 2% of commissioning can protect 100% of the project.
Evidence basis: DNV's published solar-certification work demonstrates the same principle at utility scale — independent grid-code testing and verification providing assurance to lenders and grid operators before and after commissioning. DNV performed that work; Wayfield did not.
Representative

Hospital System Turns an Energy Audit Into a Funded Roadmap

Decarbonization Strategy · United States

Client

Non-profit hospital network

The challenge

The hospital has already identified numerous energy and decarbonization opportunities. The problem isn't finding projects — it's deciding which ones should actually receive capital.

Advisory approach

Rather than a long list of recommended technologies, the roadmap ranks projects by capital cost, energy savings, carbon reduction, payback, incentives, operational risk, patient-care disruption, maintenance implications, available financing, and implementation complexity.

Result

The value isn't the audit itself — it's turning the audit into a capital program the CFO, board, and facilities team can actually execute.

A decarbonization strategy is useful only when it becomes a fundable capital plan.
Evidence basis: Mount Sinai's NYSERDA-supported program is a documented example of turning energy analysis into measured results: reported annual savings of roughly $1.52 million, 8.3 million kWh of electricity, and 125,000 MMBtu of fossil fuel. NYSERDA case study → Separately, Naples Community Hospital used an investment-grade energy audit and a five-year Energy Master Plan, coordinated with its facilities master plan, to prioritize upgrades and incorporate available rebates and incentives. Ameresco case study → Both were delivered by the organizations linked above, not by Wayfield.
Representative

School District Gets Utility-Scale-Quality Design at Non-Profit Rates

Engineering & Design · United States

Client

Public school district

The challenge

The district wants solar but has limited capital and can't afford the engineering resources normally associated with a larger commercial project — balancing engineering quality against a real public-sector budget.

Design approach

The project combines rooftop PV and parking-canopy PV with electrical-load analysis, structural review, utility coordination, site-constraint review, and long-term maintenance planning, sized to deliver both energy savings and community benefit (shaded parking, visible sustainability investment) within a constrained budget.

Result

The project concept shows that public-sector solar doesn't have to mean lower-quality engineering just because the client has a smaller budget.

Public-sector budgets require smarter engineering — not less engineering.
Evidence basis: Dysart Unified School District (Arizona) is a U.S. Department of Energy Better Buildings-recognized example of a district deploying PV across multiple schools, combining rooftop and shade-structure installations, including a system at Kingswood Elementary School. DOE Better Buildings showcase → That work was delivered for Dysart USD, not by Wayfield; exact system sizes should be confirmed against the district's own records before being cited as a specific figure.
Representative

Interconnection Screening Opens a New Market Before Capital Is Committed

Development Advisory · Canada

Client

Renewable developer entering a new Canadian jurisdiction

The challenge

The developer has experience in U.S. markets and is considering expansion into Canada. The temptation is to apply the U.S. development playbook directly — but connection procedures, available capacity, utility responsibilities, and approval timelines differ materially by jurisdiction.

Screening approach

Before committing significant engineering capital, the development screen assesses applicable provincial connection rules, transmission vs. distribution connection, hosting capacity, existing infrastructure, connection application requirements, study requirements, expected process stages, upgrade exposure, market/offtake structure, and permitting requirements.

Result

The developer can determine whether the new market justifies further investment before spending heavily on detailed engineering.

Entering a new market should begin with a connection strategy — not a land purchase.
Evidence basis: Ontario's IESO publishes a defined, multi-stage connection process — prepare application, obtain conditional approval, design/build, market participation, equipment registration, and commissioning — each a distinct stage with its own requirements. IESO connection process → Ontario has also been developing standardized hosting-capacity information to help developers identify where new distributed resources can connect. Specific stage durations vary by project and should be confirmed directly with IESO rather than assumed from this summary.
Representative

Grid-Compliant Design for a Utility-Scale Project

Engineering & Design · GCC

Client

Regional renewable-energy developer

The challenge

The project needs to satisfy two audiences at once — the grid operator and the lenders. A design that merely produces energy isn't sufficient; it needs to demonstrate grid-code compliance, reactive-power capability, plant-control functionality, protection, SCADA, forecasting/communications, performance testing, bankability, and long-term reliability.

Engineering approach

The design package is developed around both local grid requirements and international lender technical-diligence expectations simultaneously, rather than treating grid compliance and bankability as separate reviews.

Result

The engineering objective becomes more than "design the plant" — it becomes designing a plant that can survive grid review, technical due diligence, and lender scrutiny together.

A bankable design and a grid-compliant design should be the same document, not two.
Evidence basis: Saudi Arabia's 300 MW Sakaka PV project, developed by ACWA Power, demonstrates utility-scale renewable development, grid connection, and project financing in this market — ACWA Power reported connecting Sakaka PV to the national grid ahead of commercial operation. ACWA Power announcement → More recently, Masdar and consortium partners reached financial close on the 2 GW Al Sadawi solar project with approximately $1.1 billion in project financing from eight regional and international lenders. Masdar announcement → Both projects were delivered by ACWA Power and Masdar respectively, not by Wayfield.
Representative

BESS Procurement RFP Structured Around Real Degradation

RFP & Procurement Support · Africa

Client

Government / state energy authority

The challenge

Battery vendors commonly present attractive headline specifications — "20-year system life." What a procurement authority actually needs to know is how much usable capacity the system will deliver in year 1, year 5, year 10, and year 15 under the contracted operating profile.

RFP structure

Instead of evaluating batteries primarily on $/kWh, initial capacity, warranty headline, and round-trip efficiency, the procurement requires bidders to provide guaranteed usable capacity at COD, year 5, year 10, year 15, and year 20, and to define the operating assumptions behind that guarantee: cycles/year, depth of discharge, temperature, C-rate, availability, auxiliary consumption, state-of-charge window, augmentation, cell replacement, and warranty exclusions.

African-market relevance

This structure matters more as African utilities move toward larger storage deployments. The World Bank's Mauritania battery energy storage initiative is focused on grid-connected storage, renewable integration, and grid stability, with the technical and contractual structure of the procurement worked out before tendering. World Bank → The African Development Bank is separately supporting a Southern African Power Pool energy-storage strategy covering investment planning, regulatory review, and pilot projects. AfDB →

Result

The procurement decision shifts from "which battery has the lowest $/kWh" to "which bidder provides the lowest risk-adjusted lifetime cost of delivered storage capacity."

A battery warranty is only useful if the contract defines exactly what performance is being guaranteed.
Evidence basis: World Bank Mauritania battery storage initiative and AfDB Southern African Power Pool energy-storage strategy support project, both linked above — real, ongoing development-finance programs. Wayfield is not a party to either program; they're cited to show the market context this RFP structure responds to.

Note: this page cites regions (including Africa) to illustrate service capability. Wayfield's current active footprint is listed on the Footprint section of the homepage — check there for where the firm is actively engaged today.